Green light for revising budgets up

02 January 2019
Issue: 7822 / Categories: Legal News , Procedure & practice
printer mail-detail

Bar for what constitutes a significant development should not be set too high

Claimants can revise budgets upwards if more disclosure than expected is needed, representing a ‘significant development’, a High Court master has held.

Ruling in Ohoud Al-Najar (a protected party) v the Cumberland Hotel [2018] EWHC 3532 (QB), Master Davison agreed a 78% budget increase of £49,185 to £111,811 after the expected 20 to 30 lever arch files of documents turned out to be 55 lever arch files. He outlined five broad principles, including that whether a development is ‘significant’ is a question of fact; if what occurred should reasonably have been anticipated it will probably not be ‘significant’ or a ‘development’; and the development can occur in the normal course of litigation.

‘As a matter of policy, it seems to me that the bar for what constitutes a significant development should not be set too high because, otherwise, parties preparing a budget would always err on the side of caution by making overgenerous (to them) assessments of what was to be anticipated,’ he said.

The case concerned a shocking incident where a violent criminal gained access to the rooms where nine members of an extended family were sleeping and attacked three sisters with a claw hammer, causing serious facial and head injuries. Liability was complex.

City University’s Professor Dominic Regan (pictured), NLJ columnist, said: ‘This is a rare and overdue steer as to when a budget can properly be varied.

‘We are more than five years on from implementation and yet practitioners stumble around as if blindfolded.’

Francis Kendall, vicechairman of the Association of Costs Lawyers (ACL), said: ‘The ACL’s surveys over the five years since costs budgeting came into force have consistently shown that solicitors are not making enough applications to revise their budgets, when we all know in practice how often they are blown off course by events that were not reasonably foreseeable at the time they were set. Failing to revise a budget in such circumstances is just storing up problems for the later assessment of costs.

‘We urge solicitors to learn from this case and keep in mind the need to update their budgets when the situation demands it.’

Issue: 7822 / Categories: Legal News , Procedure & practice
printer mail-details

MOVERS & SHAKERS

NLJ career profile: Liz McGrath KC

NLJ career profile: Liz McGrath KC

A good book, a glass of chilled Albarino, and being creative for pleasure help Liz McGrath balance the rigours of complex bundles and being Head of Chambers

Burges Salmon—Matthew Hancock-Jones

Burges Salmon—Matthew Hancock-Jones

Firm welcomes director in its financial services financial regulatory team

Gateley Legal—Sam Meiklejohn

Gateley Legal—Sam Meiklejohn

Partner appointment in firm’s equity capital markets team

NEWS

Walkers and runners will take in some of London’s finest views at the 16th annual charity event

Law school partners with charity to give free assistance to litigants in need

Could the Labour government usher in a new era for digital assets, ask Keith Oliver, head of international, and Amalia Neenan FitzGerald, associate, Peters & Peters, in this week’s NLJ

An extra bit is being added to case citations to show the pecking order of the judges concerned. Former district judge Stephen Gold has the details, in his ‘Civil way’ column in this week’s NLJ

The Labour government’s position on alternative dispute resolution (ADR) is not yet clear

back-to-top-scroll