Arrested development

21415
Development in lockdown: the pitfalls of an approaching deadline & compliance with permission conditions. William Tyzack reports
  • Minimal commencement of works: an obvious solution?
  • Difficulty in complying with pre-commencement conditions: the options available.
  • Coronavirus: challenges of protecting the workforce.

Pursuant to s 91 of the Town and Country Planning Act 1990 (TCPA 1990) development work subject to a grant of planning permission must be begun within a period of three years, unless the planning authority has imposed, when granting permission, a different duration (whether longer or shorter). It is, furthermore, not permissible for a planning authority to extend the deadline by agreement with the landowner or developer. Conditions controlling the way in which the planning permission must be implemented may also be imposed by the planning authority, which may include works that are required to take place before the development work begins. These ‘pre-commencement works’ could include, for instance, discontinuance of any existing land use, removal of buildings, certain access or drainage works, or landscaping.

While recent relaxation of lockdown restrictions, coupled with the modification of the government’s ‘stay-at-home’ message

If you are not a subscriber, subscribe now to read this content
If you are already a subscriber sign in
...or Register for two weeks' free access to subscriber content

MOVERS & SHAKERS

Anthony Collins—20 promotions

Anthony Collins—20 promotions

20 promotions mark major people investment at national law firm, Anthony Collins

Sidley—Elaine Whiteford

Sidley—Elaine Whiteford

Sidley adds competition litigator Elaine Whiteford in London

Charles Russell Speechlys—Claudina D’Costa

Charles Russell Speechlys—Claudina D’Costa

Charles Russell Speechlys welcomes Claudina D’Costa as Director of Client Development Marketing

NEWS
The 25th Pro Bono Week begins today until 6 November, with events hosted by law firms, chambers, law schools and charities across the UK
Pro bono is celebrating a silver anniversary, with initiatives putting businesses and students at the heart of access to justice
Choosing the wrong expert can cost a clinical negligence claimant more than their case
Judges risk weakening their own independence by staying silent over government reforms, a leading public lawyer argues
A discount on damages does not automatically mean an equivalent haircut for legal costs in military deafness claims
back-to-top-scroll